Waste Incineration Plants

Waste Incineration Plants

General Contractor / Employer: Hochtief EfW Poznań s.c.

Implementation: IV Q 2013 – IV Q 2016

Scope of works: design and construction of electrical systems, including a 110kV cable line, including the design and installation of sanitary systems

General Contractor / Employer: Hitachi Zosen Inova Ltd.

Implementation: II Q 2014 – IV Q 2016

Scope of works: design, construction and commissioning of a 110/15kV station with a 20 MVA power transformer, high voltage instruments and security systems

The website uses cookies

As part of our website, we use cookies to provide you with services at the highest level, including in a manner tailored to individual needs. Using the website without changing the cookie settings means that they will be stored on your end device. You can change your cookie settings at any time. More details in ours "Cookies policy".